Latest News
20.12.2016
Retrofit / Modification Work for Bridges No. 8 and 9 at Lusail

Retrofit works to include the following major activities related to Concrete Bridges No. 8 and 9 connecting Qetaifan Islands with the Main Land in Lusail City

• Excavation excluding Shoring and Dewatering.
• Demolition of Concrete Elements
• Re-Construction of Demolished Concrete Elements including Steel Reinforcement, Formwork and Concrete Pouring.
• Demolition of Concrete Bearing Plinth.
• Rebar Anchoring and Grouting between existing and New/Re-Constructed concrete elements.
• Backfilling Work where necessary.
• Removal of Underground Micro Piles.